Weekly Update: Planned Roadwork
Date: October 21-25, 2024
Dear Residents,
Here are the roadwork notices from the Public Works Department for the upcoming week:
Tuesday - Thursday (October 22-24, 2024):
We will be completing patch paving work on Rickert Road from 152 to Mill Road. There will be no full road closures; lane restrictions will be in place.
Wednesday - Friday (October 23-25, 2024):
A crew will be on Upper Church Road performing crack sealing in preparation for chip seal work scheduled for spring.
If you have any questions, please contact Budd Hutchinson at 215-453-6000, ext. 230.
Thank you, and have a great week!